Quantcast
Channel: Savannah, GA - Blog
Browsing all 26 articles
Browse latest View live

September 3, 2015 Update

Recent rainfall has required the use of anticipated adverse weather days, but progress continues to be made.  Initial backfill has been placed on the south side of President Street and is awaiting...

View Article



September 15, 2015 Update

Despite continuous rainfall recently, crews continue to make progress.  One positive attribute of the rainfall is its natural way of consolidating soil as it soaks into the recently placed sandy...

View Article

September 24, 2015 Update

Wick Drain installation crews have mobilized to the site and are setting up for installation of wick drains along the south side of President St. Wick drains will be installed to a depth of 40’ on a 5’...

View Article

Oct. 2, 2015 Update

Wick Drain installations were completed this week on the south side of President Street and along a new section of General McIntosh Boulevard.  Now that wick drains have been installed,  crews have...

View Article

October 9, 2015 Update

Following the completion of wick drain installations, crews are placing the additional foot of sand over wick drains and continuing to place additional lifts of surcharge material.  The surcharge...

View Article


October 21, 2015 Update

Surcharge material (material used for its weight to accomplish consolidation settlement) continues to be placed along the new General McIntosh Boulevard roadway and along the south side of President...

View Article

October 30, 2015 Update

Surcharge material continues to be placed along the south side of President Street. This material will continue to be placed over the next three weeks at a slightly slower rate (one foot per week)...

View Article

November 10, 2015 Update

Surcharge material continues to be placed along the south side of President Street and General McIntosh Boulevard.  This material will continue to be placed over the next few weeks until design...

View Article


November 16, 2015 Update

Surcharge material continues to be placed along the south side of President Street and General McIntosh Boulevard.  This material will continue to be placed over the next few weeks until design...

View Article


November 30, 2015 Update

At this time, surcharge material placement has been completed across the entire project (south side of President Street and General McIntosh), except for a small section of the south side of President...

View Article

December 14, 2015 Update

The placement of surcharge material across the project has been completed.  Since reaching this completion temporary seeding and straw mulch has been applied to areas that will not be disturbed for an...

View Article

January 8, 2016 Update

Now that surcharge placement on the project has been completed, earth work operations have significantly slowed.  As scheduled, the surcharge will require a period of time for consolidation of under...

View Article

January 25, 2016 Update

Overall activity on the project has slowed some, but although you don’t see as much heavy equipment up and down the site, after placement of the surcharge material on the south side of President...

View Article


August 8, 2016 Update

Stormwater and Water utility lines along the New General McIntosh Blvd are nearing completion. Crews are currently installing water main casing under General McIntosh Blvd. On the south side of...

View Article

August 17, 2016 Update

Water utility lines along the new General McIntosh Blvd are nearing completion. Crews are excavating a pit at the intersection of President Street and the new General McIntosh Blvd intersection in...

View Article


September 7, 2016 Update

Crews continue to work at the intersection of President Street and the new General McIntosh Blvd in preparation to bore a water main under President Street.  This method of installation will allow...

View Article

November 2, 2016 Update

Crews continue to work on utility connections at the intersection of President Street and the new General McIntosh Blvd.  The 24” water main core under President Street is complete. Water lines are...

View Article


December 2, 2016 Update

Crews have nearly completed this phase of utility work at the intersection of President Street and the new General McIntosh Blvd.  The last of the stormwater inlets and pipes are being installed.  On...

View Article

December 15, 2016 Update

Traffic shift on President Street to begin Dec. 15 Motorists traveling on President Street should be aware of a major planned traffic shift scheduled to begin Thursday, December 15. The shift will...

View Article

December 16, 2016 Update

Utility work on the South side of President Street is complete.  Asphalt and striping was completed this week and this phase of the traffic shift is underway.  Four lanes of traffic will be maintained...

View Article
Browsing all 26 articles
Browse latest View live




Latest Images