September 3, 2015 Update
Recent rainfall has required the use of anticipated adverse weather days, but progress continues to be made. Initial backfill has been placed on the south side of President Street and is awaiting...
View ArticleSeptember 15, 2015 Update
Despite continuous rainfall recently, crews continue to make progress. One positive attribute of the rainfall is its natural way of consolidating soil as it soaks into the recently placed sandy...
View ArticleSeptember 24, 2015 Update
Wick Drain installation crews have mobilized to the site and are setting up for installation of wick drains along the south side of President St. Wick drains will be installed to a depth of 40’ on a 5’...
View ArticleOct. 2, 2015 Update
Wick Drain installations were completed this week on the south side of President Street and along a new section of General McIntosh Boulevard. Now that wick drains have been installed, crews have...
View ArticleOctober 9, 2015 Update
Following the completion of wick drain installations, crews are placing the additional foot of sand over wick drains and continuing to place additional lifts of surcharge material. The surcharge...
View ArticleOctober 21, 2015 Update
Surcharge material (material used for its weight to accomplish consolidation settlement) continues to be placed along the new General McIntosh Boulevard roadway and along the south side of President...
View ArticleOctober 30, 2015 Update
Surcharge material continues to be placed along the south side of President Street. This material will continue to be placed over the next three weeks at a slightly slower rate (one foot per week)...
View ArticleNovember 10, 2015 Update
Surcharge material continues to be placed along the south side of President Street and General McIntosh Boulevard. This material will continue to be placed over the next few weeks until design...
View ArticleNovember 16, 2015 Update
Surcharge material continues to be placed along the south side of President Street and General McIntosh Boulevard. This material will continue to be placed over the next few weeks until design...
View ArticleNovember 30, 2015 Update
At this time, surcharge material placement has been completed across the entire project (south side of President Street and General McIntosh), except for a small section of the south side of President...
View ArticleDecember 14, 2015 Update
The placement of surcharge material across the project has been completed. Since reaching this completion temporary seeding and straw mulch has been applied to areas that will not be disturbed for an...
View ArticleJanuary 8, 2016 Update
Now that surcharge placement on the project has been completed, earth work operations have significantly slowed. As scheduled, the surcharge will require a period of time for consolidation of under...
View ArticleJanuary 25, 2016 Update
Overall activity on the project has slowed some, but although you don’t see as much heavy equipment up and down the site, after placement of the surcharge material on the south side of President...
View ArticleAugust 8, 2016 Update
Stormwater and Water utility lines along the New General McIntosh Blvd are nearing completion. Crews are currently installing water main casing under General McIntosh Blvd. On the south side of...
View ArticleAugust 17, 2016 Update
Water utility lines along the new General McIntosh Blvd are nearing completion. Crews are excavating a pit at the intersection of President Street and the new General McIntosh Blvd intersection in...
View ArticleSeptember 7, 2016 Update
Crews continue to work at the intersection of President Street and the new General McIntosh Blvd in preparation to bore a water main under President Street. This method of installation will allow...
View ArticleNovember 2, 2016 Update
Crews continue to work on utility connections at the intersection of President Street and the new General McIntosh Blvd. The 24” water main core under President Street is complete. Water lines are...
View ArticleDecember 2, 2016 Update
Crews have nearly completed this phase of utility work at the intersection of President Street and the new General McIntosh Blvd. The last of the stormwater inlets and pipes are being installed. On...
View ArticleDecember 15, 2016 Update
Traffic shift on President Street to begin Dec. 15 Motorists traveling on President Street should be aware of a major planned traffic shift scheduled to begin Thursday, December 15. The shift will...
View ArticleDecember 16, 2016 Update
Utility work on the South side of President Street is complete. Asphalt and striping was completed this week and this phase of the traffic shift is underway. Four lanes of traffic will be maintained...